The holidays at the end of each year is never a quiet season for our school. From 5th December 2016 when the SPM examinations ended, there is a busyness in SMK Convent Sentul not matched by many other schools. The hive of activities executed by about 15 teams of workmen is closely supervised by their bosses on site in school. The teams' bosses works in close liaison and are spearheaded by Mr. Lee Geok Ai, Chairman of the Board of Governors. I and Pn Wang and the team of school administrators and teachers and office staff work together with these crews to upgrade the school.
The school at 8.30 am in the morning will look different from the school at 12.00 noon and at 5.00 pm because the progress of the upgrading works done by the various crews of men. Mr. Lee comes in personally many times to assess the problems faced by the various crews. His expertise empower them to resolve the problems faced. Photos of progress of work sent through the what apps group helped him monitor and push the pace of work to reach our deadline before school reopens on 3rd Jan 2017. Who are these teams and what do they do?
Let me list them.
1. Hackers and cement works.
2. Tilers
3. Painters
4. Plumbers and Piping and Pumps
5. Electricians and Fans Installation
6. Landscapers
7. Ironwork
8. Furniture repair
9. Furniture supply
10. Ceiling and Roofs Repair
11. Automatic bell Installation
12. Glass works
13. Bookshop Renovation
14. Frog Room and ICT upgrades
15. Banners Installation
16. Administrators and Teachers and Office Staff
I shall show some before and after upgrades photos.
6 classrooms with major cracks in their cement floor. Classroom floors are tiled for the first time in CS long history of 76 years. 4 Cempaka floor after being tiled. |
Old rusty steel cabinets with crooked doors were repainted and realigned. They looked totally brand new! We are so delighted with the big difference. |
The canteen block and the Form 4 block being repainted. |
New colours for Form 4 block |
The erosion at the bottom of the assembly platform is being arrested by repacking the soil and returfing it with new grass. The field will be improved by new soil and returfing. New shrubs are planted near the zincalum block to provide more shade for the 3 classrooms there. Paths are filled with river pebbles add a fresh look to our grounds. Canteen benches were also repaired .Mr Lee was concerned that the canteen benches would spoil the girls' new uniform when they came back to school. Mr Lee got Daniel Yong Shi Yuen and his team of men from BeauTop to repair them all.
3 lorry loads of soil for returfing and tiling |